1Nov

Russel Lee Park, Sidewalk Replacement

Russel Lee Park, Sidewalk Replacement

IMG_0712

Project Description

This project consists of excavating the existing walkways and replacing them with a newly stamped concrete walking path, bench pads and site furnishings.

Project Details

  • Client: Metro Parks & Recreation
  • Architect/Engineer: Metro Parks & Recreation
  • Builder/General Contractor: APC
  • Budget: N/A
  • Expected Start and Finish Dates: November 2nd – December 2nd, 2017

Project Gallery

IMG_0701
IMG_0707
IMG_0702
IMG_0703
IMG_0793
IMG_0799
IMG_0798
IMG_0804
IMG_1213
IMG_1214
IMG_1222
IMG_1216
IMG_1218
IMG_1219
IMG_1220
IMG_1221
Read More
1Aug

Hopkins Lane, Sidewalk & D.I.P

Hopkins Lane Sidewalk Installation and Storm Drainage Improvments

IMG_6391

Project Description

This project consists of the furnishing and installing approximately 3,900’ of 5’ wide concrete sidewalk, curb ramps, concrete driveway aprons, selective paving, striping, storm and sanitary sewers.

Project Details

  • Client: City of Jeffersonville
  • Architect/Engineer: Jacobi, Toombs &Lanz Inc.
  • Builder/General Contractor: APC
  • Budget: $315,000
  • Expected Start and Finish Dates: June 2017 to August 2017

Project Gallery

IMG_6393
IMG_6399
IMG_6405
IMG_6408
IMG_6409
IMG_6411 (2)
IMG_6414
IMG_6420
IMG_6421
IMG_6424
IMG_6427
IMG_6428
IMG_6429
IMG_6430
IMG_0500
IMG_0502
IMG_0499
IMG_0448
IMG_0452
IMG_0464
IMG_0467
IMG_0469
IMG_0482
IMG_0489
IMG_0492
IMG_0457
IMG_0459
Read More
21Jun

C2 Event Center, Site Demo & Lot Remodel

C2 Event Center, Site Demo & Lot Remodel

IMG_6362 (2)

Project Description

For this project we performed selective construction and site demo for a new building/event center. The project consisted of sitegrading for building pad, installing irrigation sleeves, sidewalks, curbs, curb ramps, driveway/entrance, wheel stops, signage, asphalt parking lot repairs, sealcoat, and striping.

Project Details

  • Client: Kelley Construction
  • Architect/Engineer:
  • Builder/General Contractor: Kelley Construction (General contractor) APC (Subcontractor)
  • Budget: $176,000
  • Expected Start and Finish Dates: April 2016 to June 2017

Project Gallery

IMG_6361 (2)
IMG_6362 (3)
IMG_6332
IMG_6335
IMG_6337
IMG_6338
IMG_6339
IMG_6347
IMG_6349
IMG_6350
IMG_6351
IMG_6356
IMG_6357
IMG_6358 (2)
IMG_6358
IMG_6359
IMG_6360 (2)
IMG_6361 (2)
IMG_6361

Project Video

Read More
20Jun

Chestnut Street, Streetscape

Chestnut Street, Streetscape

Chestnut St- Streetscape6

Project Description

This project included milling and repaving the existing asphalt pavement.We also removed and replaced the concrete sidewalks to redesign the street corner at Chestnut St and Wall St. We then created a curbed bump-out that swells out into the road to form a defined parking area for the nearby residents. This streetscape really enhanced the aesthetic and created a safe area for pedestrians and parked cars.

Project Details

  • Client: City of Jeffersonville
  • Architect/Engineer: City of Jeffersonville
  • Builder/General Contractor: APC
  • Budget: $45,000
  • Expected Start and Finish Dates: April 2017 to June 2017

Project Gallery

Chestnut St- Streetscape
Chestnut St- Streetscape2
Chestnut St- Streetscape3
Chestnut St- Streetscape4
Chestnut St- Streetscape5

Project Video

Read More
20Jun

Autumn Grove, Concrete Work & D.I.P

Autumn Grove, Concrete Work & D.I.P

IMG_6214

Project Description

For this new subdivision we have done all concrete work including driveways, walkways, sidewalks, stairs, curbs and gutters, and drain pans. We created a detention base to collect and properly drain overflow storm water. All of the roadways have been base paved by usand we will finish the paving process once all other construction on-site has finished, ensuring a long-lasting roadway.

Project Details

  • Client: Neace Ventures
  • Architect/Engineer: John G. Brinkworth
  • Builder/General Contractor: Neace Ventures
  • Budget: $250,000
  • Expected Start and Finish Dates: 2014  (Expected) Fall of 2018

Project Gallery

Automn Grove- Detention Base
IMG_6211
IMG_6212
IMG_6213
Read More