Wesley Chapel, Seal-coat/Striping

Wesley Chapel Parking Lot Seal-coating and Striping

IMG_1504

Project Description

This project consisted of prepping the existing asphalt to apply rubber crack sealant to cracks throughout the parking lot and drive. APC then applied a seal coating to the entire parking lot and drive and re-striped the entire parking lot and drive to original design. APC installed a 6″ PVC French drain wrapped in Geo-textile fabric to eliminate drainage issue in the SE corner in the rear of the parking lot; as well as repairing the existing asphalt in this area.

Project Details

  • Client: Wesley Chapel
  • Architect/Engineer:
  • Builder/General Contractor: Allterrain Paving & Construction (APC)
  • Budget: N/A
  • Expected Start and Finish Dates: July 16 – July 26, 2018

Project Gallery

IMG_1489
IMG_1491
IMG_1495
IMG_1498
IMG_1505
IMG_1509
IMG_1513
IMG_1522
IMG_1526
IMG_1530
IMG_1532
IMG_1533
IMG_1534
IMG_1536
IMG_1538
IMG_1540
IMG_1541
IMG_1542
IMG_1545
IMG_1549
Read More
21Jun

Progress Way, Asphalt Pavement Repair

Progress Way, Asphalt Pavement Repair

IMG_6157 (1)

Project Description

For this project we were sent in to fix the uneven and rough transition concerning where the roadway and the bridge meet. This transition had sunken over time which caused the roadway to be uncomfortable and unsafe for drivers. We were able to complete repairs on both ends of the bridge in 1 day causing minimal disruption to traffic flow on this busy roadway. For this project we used our Infrared Asphalt Recycler Machine, therefore there was no need of milling. With this technology we heated the existing asphalt back up to factory standards, and then we add rejuvenating oil, which brought the asphalt back to life. At this point we were able to rake the asphalt to properly distribute it, and at that time the asphalt is rolled and sealed to create a smooth and long lasting surface.

Project Details

  • Client: Town of Clarksville
  • Architect/Engineer: Bradley Cummings- Public Works Director
  • Builder/General Contractor: APC
  • Budget: $5000
  • Expected Start and Finish Dates:Started & Completed on June 1st2017