Hopkins Lane Sidewalk Installation and Storm Drainage Improvments

Project Description
This project consists of the furnishing and installing approximately 3,900’ of 5’ wide concrete sidewalk, curb ramps, concrete driveway aprons, selective paving, striping, storm and sanitary sewers.
Project Details
- Client: City of Jeffersonville
- Architect/Engineer: Jacobi, Toombs &Lanz Inc.
- Builder/General Contractor: APC
- Budget: $315,000
- Expected Start and Finish Dates: June 2017 to August 2017