North Harrison Community Schools – Repave, Seal Coat, Stripe

PROJECT DESCRIPTION

This project included mass excavation/grading, base rock installation and grading, paving, and striping for the new parking lot in front of the new building addition. The project also included asphalt re-surfacing of the North Harrison campus primary roadway. Demolition of the existing concrete island near the North Harrison Middle School entrance. Crack filling, seal coating, and re-striping of all parking lots as well as the ball field path at the North Harrison campus. Crack filling, seal coating of all three lots at Morgan Elementary.

PROJECT DETAILS
  • Client: North Harrison Community Schools
  • Architect/Engineer: Kovert Hawkins Architects, Inc.
  • Construction Manager: James L. Shireman, Inc.
  • Builder/General Contractor: APC
  • Budget: $337,700
  • Expected Start and Finish Dates: July – November 2018
IMG_1577
PROJECT GALLERY
Read more

Wesley Chapel, Seal-coat/Striping

PROJECT DESCRIPTION

This project consisted of prepping the existing asphalt to apply rubber crack sealant to cracks throughout the parking lot and drive. APC then applied a seal coating to the entire parking lot and drive and re-striped the entire parking lot and drive to the original design. APC installed a 6″ PVC French drain wrapped in Geo-textile fabric to eliminate drainage issues in the SE corner in the rear of the parking lot; as well as repair the existing asphalt in this area.

PROJECT DETAILS
  • Client: Wesley Chapel
  • Architect/Engineer:
  • Builder/General Contractor: Allterrain Paving & Construction (APC)
  • Budget: N/A
  • Expected Start and Finish Dates: July 16 – July 26, 2018