North Harrison Community Schools - Repave, Seal Coat & Stripe

IMG_1577

Project Description

This project included mass excavation/grading, base rock installation and grading, paving and striping for the new parking lot in front of new building addition.  Project also included asphalt re-surfacing of North Harrison campus primary roadway.  Demolition of existing concrete island near the North Harrison Middle School entrance.  Crack filling, seal coating and re-striping of all parking lots as well as the ball field path at the North Harrison campus.  Crack filling, seal coating of all three lots at Morgan Elementary.

Project Details

  • Client: North Harrison Community Schools
  • Architect/Engineer: Kovert Hawkins Architects, Inc.
  • Construction Manager: James L. Shireman, Inc.
  • Builder/General Contractor: APC
  • Budget: $337,700
  • Expected Start and Finish Dates: July – November 2018

Project Gallery

IMG_1566
IMG_1567
IMG_1571
IMG_1573
IMG_1595
IMG_1598
IMG_1584
IMG_1583
IMG_1585
IMG_1587
IMG_1586
IMG_1604
IMG_1605
IMG_1606
IMG_1607
IMG_1574
1
2
8
3