North Harrison Community Schools – Repave, Seal Coat, Stripe

PROJECT DESCRIPTION

This project included mass excavation/grading, base rock installation and grading, paving, and striping for the new parking lot in front of the new building addition. The project also included asphalt re-surfacing of the North Harrison campus primary roadway. Demolition of the existing concrete island near the North Harrison Middle School entrance. Crack filling, seal coating, and re-striping of all parking lots as well as the ball field path at the North Harrison campus. Crack filling, seal coating of all three lots at Morgan Elementary.

PROJECT DETAILS
  • Client: North Harrison Community Schools
  • Architect/Engineer: Kovert Hawkins Architects, Inc.
  • Construction Manager: James L. Shireman, Inc.
  • Builder/General Contractor: APC
  • Budget: $337,700
  • Expected Start and Finish Dates: July – November 2018
IMG_1577
PROJECT GALLERY
Read more

M. Fine Lot Development

PROJECT DESCRIPTION

This project consisted of excavating and grading the existing topography to install a new parking lot. APC began by installing a compacted stone base for the new parking lot and the alley way behind the parking lot. An electrical conduit and concrete base for new lighting poles were installed, as well as drainage structures and drainage pipes. Some of the existing sidewalk was removed and replaced with new ADA compliant crosswalks. A concrete privacy wall with decorative limestone veneer was built along the perimeter of the lot facing Main Street. A wooden privacy fence was built along the remaining perimeter. APC installed an HMA Base course and HMA Surface course along with a monolithic concrete curb and gutter around the lot. APC added signs and striping to complete the construction of the lot.

PROJECT DETAILS
  • Client: New Albany Board of Public Works
  • Architect/Engineer: HMB Professional Engineers, Inc.
  • Builder/General Contractor: APC
  • Expected Start and Finish Dates: June – September 2018
finished-595x480
PROJECT GALLERY
Read more

Wesley Chapel, Seal-coat/Striping

PROJECT DESCRIPTION

This project consisted of prepping the existing asphalt to apply rubber crack sealant to cracks throughout the parking lot and drive. APC then applied a seal coating to the entire parking lot and drive and re-striped the entire parking lot and drive to the original design. APC installed a 6″ PVC French drain wrapped in Geo-textile fabric to eliminate drainage issues in the SE corner in the rear of the parking lot; as well as repair the existing asphalt in this area.

PROJECT DETAILS
  • Client: Wesley Chapel
  • Architect/Engineer:
  • Builder/General Contractor: Allterrain Paving & Construction (APC)
  • Budget: N/A
  • Expected Start and Finish Dates: July 16 – July 26, 2018
IMG_1504
PROJECT GALLERY
Read more

Wyandotte Park, Sport Court Improvements

PROJECT DESCRIPTION

This project consisted of demolishing the existing tennis court to replace it with a new futsal court, pickleball courts, and a tennis court. The existing lighting was removed and we installed new lighting for the new courts and the basketball court. Allterrain regraded multiple areas within the park to improve storm drainage and installed new storm structures and a drain pipe. Allterrain also repaved the majority of the existing walking paths within the park.

PROJECT DETAILS
  • Client: Louisville Jefferson County Metro Government/Metro Parks
  • Architect/Engineer: Louisville Jefferson County Metro Government/Metro Parks
  • Builder/General Contractor: Allterrain Paving & Construction (APC)
  • Budget: $303,000
  • Expected Start and Finish Dates: April – July 2018
IMG_1447
PROJECT GALLERY
Read more

Chadford Way, D.I.P

CHADFORD WAY, DRAINAGE IMPROVEMENT PROJECT
PROJECT DESCRIPTION

This project consists of earth regrading and building a concrete wall due to flooding issues. We also replaced the affected neighbors’ driveway and added stone and sod to complete the curb appeal after the job was completed.

PROJECT DETAILS
  • Client: MSD
  • Architect/Engineer: Trautwein Engineering
  • Builder/General Contractor: APC
  • Budget: $200,000
  • Expected Start and Finish Dates: March – May 2018
IMG_1303
PROJECT GALLERY
Read more

Woodside Drive, D.I.P

WOODSIDE DRIVE, CULVERT REPLACEMENT D.I.P
PROJECT DESCRIPTION

This project consists of removing the existing road and concrete bridge. We are installing a 10’ x 5’ precast concrete box culvert and pouring in place concrete wing walls and footers. We will then proceed with replacing the road with new asphalt and a guardrail.

PROJECT DETAILS
  • Client: Louisville Metro Public Works
  • Architect/Engineer: QK4
  • Builder/General Contractor: APC
  • Budget: N/A
  • Expected Start and Finish Dates: November 1st – November 15th 2017
IMG_0732
PROJECT GALLERY
Read more

Russel Lee Park, Sidewalk Replacement

PROJECT DESCRIPTION

This project consists of excavating the existing walkways and replacing them with a newly stamped concrete walking path, bench pads, and site furnishings.

PROJECT DETAILS
  • Client: Metro Parks & Recreation
  • Architect/Engineer: Metro Parks & Recreation
  • Builder/General Contractor: APC
  • Budget: N/A
  • Expected Start and Finish Dates: November 2nd – December 2nd, 2017
IMG_0712
PROJECT GALLERY
Read more

Vincennes St, Thermoplastic Striping

PROJECT DESCRIPTION

This project consists of thermoplastic striping and road markings along Vincennes St from Main St to Charlestown Rd. We striped all new asphalt including traffic symbols, parking spots, crosswalks, and bike lanes.

PROJECT DETAILS
  • Client: City of New Albany
  • Architect/Engineer: Clark Dietz Inc, Wes Christmas
  • Builder/General Contractor: MAC Construction & Excavating Inc
  • Budget: N/A
  • Expected Start and Finish Dates: July 11 2017 – August 31 2017
IMG_0246
PROJECT GALLERY
Read more

Hopkins Lane, Sidewalk & D.I.P

HOPKINS LANE SIDEWALK INSTALLATION AND STORM DRAINAGE IMPROVMENTS
PROJECT DESCRIPTION

This project consists of furnishing and installing approximately 3,900’ of 5’ wide concrete sidewalk, curb ramps, concrete driveway aprons, selective paving, striping, storm, and sanitary sewers.

PROJECT DETAILS
  • Client: City of Jeffersonville
  • Architect/Engineer: Jacobi, Toombs &Lanz Inc.
  • Builder/General Contractor: APC
  • Budget: $315,000
  • Expected Start and Finish Dates: June 2017 to August 2017
IMG_6391
PROJECT GALLERY
Read more

N.A Plaza, Concrete/Asphalt/Striping

NEW ALBANY PLAZA, CONCRETE CURBS/PAVING/STRIPING
PROJECT DESCRIPTION

This project consists of milling the vast majority of the parking lot to install new concrete curbs and pour new asphalt. We also striped all new asphalt and painted traffic control and handicap symbols.

PROJECT DETAILS
  • Client: Kroger
  • Architect/Engineer: Heritage Engineering
  • Builder/General Contractor: APC
  • Budget: N/A
  • Expected Start and Finish Dates: June 22nd 2017 to July 14th 2017
IMG_0217-1
PROJECT GALLERY
Read more