Autumn Grove, Concrete Work & D.I.P

PROJECT DESCRIPTION

For this new subdivision, we have done all concrete work including driveways, walkways, sidewalks, stairs, curbs, gutters, and drain pans. We created a detention base to collect and properly drain overflow stormwater. All of the roadways have been base paved by us and we will finish the paving process once all other construction on-site has finished, ensuring a long-lasting roadway.

PROJECT DETAILS
  • Client: Neace Ventures
  • Architect/Engineer: John G. Brinkworth
  • Builder/General Contractor: Neace Ventures
  • Budget: $250,000
  • Expected Start and Finish Dates: 2014  (Expected) Fall of 2018
IMG_6214-e1498194965929
PROJECT GALLERY
Read more

Applegate Lane, D.I.P

PROJECT DESCRIPTION

The Town of Sellersburg had an emergency contract to replace a failing concrete drainage structure. For this drainage improvement project, we began with excavating the existing breaking down the roadway and old-style concrete culvert to install a brand new concrete box culvert. After excavating the site, we then regraded the drainage bank area to ensure proper water flow. The new culvert box is 10’ wide by 4’ tall and 60’ long. After placing the new culvert boxes we began to form and pour concrete wing walls on each end of the structure. We then added a rip-rap stone base and paved a new roadway.

PROJECT DETAILS
  • Client: Town of Sellersburg
  • Architect/Engineer: Jacobi, Toombs & Lanz Inc.
  • Builder/General Contractor: APC
  • Budget: $120,000
  • Expected Start and Finish Dates: May 25th → June 13th 2017
20170608_143335
PROJECT GALLERY
Read more

Ground Effects LTD., New Parking Lot

PROJECT DESCRIPTION

For this project, APC was responsible for full site development for Ford’s production lot of 10,000 square yards. We began with excavating the site and leveling out the ground. Once we had an even surface we placed and compressed the rip-rap stone base to prepare for asphalt paving. APC performed the asphalt paving and striping of the new lot as well.

PROJECT DETAILS
  • Client: Ground Effects LTD.
  • Architect/Engineer: APC
  • Builder/General Contractor: APC
  • Budget: $90,000
  • Expected Start and Finish Dates: November 2016 to December 2016
IMG_1406
PROJECT GALLERY
Read more

LG&E Restoration Contract

PROJECT DESCRIPTION

APC is responsible for repairing the disturbed areas of all roadways, concrete street pads and sidewalks where LG&E has completed the renewal of gas pipe work. This restoration contract that LG&E is performing takes place within the downtown metro area of Louisville, KY. So far, APC has completed 13 projects for this contract.

PROJECT DETAILS
  • Client: LG&E
  • Architect/Engineer: David McQuire and Debra Davis from LG&E
  • Builder/General Contractor: APC
  • Budget: Unit Price Contract
  • Expected Start and Finish Dates: Contract finishes in April 2021